This Fast Track Design/Build project was procured through the PPEA Guidelines for a new 1.25 MGD ENR treatment plant, 1.8 MGD pump station, 11,000’ of 24” gravity sewer 9000’ of 16” force main and 5000’ of 20” outfall pipe to the Nottoway River. Design includes all permitting and approval with DEQ and VDH. Design has been phased to allow early completion of the pump station and pipelines to service a new elementary school. Construction consists of the following: 1) New dry pit submersible pump station 2) Headworks with strip screen, bypass channel, and grit removal process 3) Oxidation ditch 4) 2-50’ diameter clarifiers 5) Disc filter and UV disinfection system 6) Pos -aeration 7) RAS/WAS pump station 8) 2 digesters with centrifuge for dewatering 9) Complete plant controls with emergency generator backup.
|